Rock Creek Stormwater

Project Type:
Storm Water
Project Status: 
Completed

Project consists of unclogging and relocating the outfall for the stormwater collection system from Rock Creek Drive near the west entrance of the fairgrounds parking lot to Rock Creek.


Contract: $64k Wallis Engineering, $128k Crestline Construction
Progress: 100%
Budget: $179k / $41k Spent 
Funding: $149k Street Fund, $30k CIP Fund
Planned Completion Date: December 31, 2022

Status Updates

November 2022 - Most of the project updates were provided through the Rock Creek Pump Station project. The stormwater portion has reached substantial completion and no ponding on Rock Creek Drive has occurred, even with the heavy rains!  Some additional mitigation work may need to occur in the spring along the bank of Rock Creek, and no additional public impact is anticipated.

September 2021 - The construction phase was awarded to Crestline Construction in June. Due to delays in materials procurement, construction will begin in April, 2022.